How to Verify a Contractor's HVAC Quote
By Danish Javaid, founder & editor · Published · Updated

To verify an HVAC quote, check three things against paper: that the proposed capacity is roughly 95 to 115 percent of the calculated cooling load at design conditions (with sensible and latent each covered), that the rating on the quote matches the AHRI certificate for the exact equipment, and that every bid you compare includes the same work. A quote that lists a brand, a tonnage and a price passes none of these checks until it comes with a load report and a model-by-model scope.
The audit at a glance
| Document | What to verify | Red flag |
|---|---|---|
| Load report | Same house as the quote: address, rooms, insulation, glazing, leakage, duct location; heating, sensible, latent and total cooling shown | No report, or loads copied from the old unit |
| Equipment selection | Total, sensible and latent capacity at your design conditions for the exact models | Only nominal tons or load ÷ 12,000 |
| AHRI certificate | SEER2, EER2 and HSPF2 for the exact outdoor unit, coil and blower | "Up to" brochure ratings on a lower-rated combination |
| Scope | Ducts, line set, electrical, drains, permit, controls, startup, warranty each itemized | One line reading "new system" |
| Price | Gross price, confirmed incentives, financing, change-order terms | Incentives subtracted without written approval |
Check the size arithmetic yourself
Ask for the report, then compare the selected model's published capacity at your conditions with the load. A nameplate or load ÷ 12,000 is a starting point only; for a furnace use rated output rather than input, since AFUE is a seasonal efficiency rather than a capacity (the furnace sizing guide shows the conversion). These windows are 95% to 115% of the load for straight cooling units; heat pumps and furnaces use different limits, and exact numbers depend on the Manual S edition.
| Calculated total cooling load (BTU/h) | 95% of load | 115% of load |
|---|---|---|
| 24,000 | 22,800 | 27,600 |
| 30,000 | 28,500 | 34,500 |
| 36,000 | 34,200 | 41,400 |
| 48,000 | 45,600 | 55,200 |
Total is not enough, because sensible capacity must cover the sensible load and latent the latent. Take a report of 30,000 BTU/h total, made up of 24,000 sensible and 6,000 latent. A candidate delivering 33,000 total with 27,000 sensible and 6,000 latent is 110% and covers both. A different 33,000-total candidate with only 5,000 latent also passes on total but falls 1,000 BTU/h short on moisture. These are assumed values, not a real model.
If the quoted size is well above the window, ask why. There are legitimate reasons, such as the next available size or a planned addition, but they belong in writing next to the numbers. If you want your own benchmark first, our tonnage calculator and Manual J calculator give a screening estimate; a disagreement means ask for the inputs, not that either is wrong. The consequence of a miss is explained in oversized AC symptoms.
Make the bids comparable
Three assumed bids for the same 3-ton system. Bid B is itemized, so its line items price the work the others left out: duct sealing $900, permit $250, startup and commissioning record $350.
| Bid A | Bid B | Bid C | |
|---|---|---|---|
| Quoted price | $9,800 | $11,400 | $10,900 |
| Duct sealing | No (+$900) | Yes | No (+$900) |
| Permit | No (+$250) | Yes | Yes |
| Commissioning record | No (+$350) | Yes | No (+$350) |
| Comparable price | $11,300 | $11,400 | $12,150 |
Bid A may still be the right choice, but the decision is now about the contractor and process rather than $1,600 of missing work. Ask A and C to put the missing items in writing as inclusions or as exclusions you will cover. Also confirm each bid rests on its own load calculation, and look closely at outliers: a much lower bid may omit permits, ducts or commissioning, and a much higher one should explain what it adds.
Match the paper to the box
Request the AHRI certificate for the proposed combination. A quote promising "up to 20 SEER2" but listing a lower-rated indoor and outdoor pair is selling the brochure, and DOE regional minimums also depend on equipment type, size and where it is installed (see the SEER2 guide). The refrigerant belongs on the quote too: newer residential equipment ships with R-454B or R-32 instead of R-410A, and indoor and outdoor halves must be rated for the same refrigerant. If the quote reuses your coil or line set, ask the installer to cite the manufacturer's instruction that permits it. A working R-410A system does not have to be replaced.
On discounts: a federal heat pump credit under 25C cannot be applied to a system placed in service after December 31, 2025, so ask which program a contractor means. A state or utility rebate counts only with the approval in hand, and the quote should show who receives it and when.
Before you sign, and after the install
Have the contractor write down the final models, the commissioning documents and room-delivery checks you will receive, who handles inspection, and how deficiencies are corrected. If sizing still disagrees after resolving inputs, an independent design review is cheaper than a wrong system. After installation keep the report and startup record, and check that the labels on the equipment match the proposal; the static pressure guide explains the airflow readings that should be in that record. The contractor questions guide covers what to ask before quotes arrive.
Sources: ACCA Manual S; AHRI Directory; DOE 2023 standards FAQ; IRS: 25C not allowed after Dec. 31, 2025; EPA Technology Transitions.
Calculation guidance is reviewed against our published methodology. To report an error or request a correction, use the contact page.
Written and maintained by Danish Javaid, founder & editor. About this site.
Revision history
- : Recast as a document audit with a three-bid scope-normalization example, removing the per-square-foot scenario table.